PI065 | Overdue tasks in PMS V4.0

Performance Indicator


DefinitionThis PI captures the number of outstanding Planned Maintenance Tasks for individual vessels.
UnitPercentage
ScopeReported on a ship level
Calculation periodCaptured and reported on a quarterly basis as an average of the previous 3 months
ReferencesThis Performance Indicator - PI065 - is used by the following Key Performance Indicators
KPI036Overdue tasks in PMS
PI065Overdue tasks in PMS
Example

  • Total no. of planned maintenance tasks due in Jan, Feb and March = 80, 90, 70
  • Total no. of outstanding planned maintenance tasks as on Jan, Feb and March = 3, 5,4
  • Total no. of planned maintenance tasks due in Q1= 80+ 100 + 60 = 240
  • Total no. of outstanding planned maintenance tasks as on Q1 = 3 + 5 + 4 = 12
  • Quarterly percentage Overdue = 3.75% + 5.55% + 5.71 / 3 = 5%
External references

OCIMF TMSA 3 (Tanker Management Self-Assessment) Standard, Elements 4-1-4