PI005 | Agreed drydocking duration V4.0

Performance Indicator

This PI captures the ship’s agreed drydocking duration.


Definition

The Agreed Drydocking Duration as agreed between ship manager/owner and shipyard BEFORE the drydocking. This shall include in-water survey (IWS), modifications and repairs. Any extension of the duration which is approved (agreed) AFTER the drydocking has commenced shall NOT be taken into account.

UnitDAYS
ScopeReported on a ship level
Calculation periodCaptured and reported in the quarter the drydocking was completed.
ReferencesThis Performance Indicator - PI005 - is used by the following Key Performance Indicators
KPI010Drydocking planning performance
PI001Actual drydocking costs
PI002Actual drydocking duration
PI004Agreed drydocking budget
PI005Agreed drydocking duration
Example

Agreed drydocking duration = 14.2 days