PI001 | Actual drydocking costs V4.0
Performance Indicator
This PI captures ship’s actual drydocking costs.
| Definition | The total actual costs associated with the drydocking. This shall include in-water survey (IWS), modifications and repairs, not included in routine running costs. It also includes costs for any additional work not planned for before the drydocking. | ||||||||||||
| Unit | USD | ||||||||||||
| Scope | Reported on a ship level | ||||||||||||
| Calculation period | Captured and reported in the quarter the drydocking was completed | ||||||||||||
| References | This Performance Indicator - PI001 - is used by the following Key Performance Indicators
| ||||||||||||
Example
Actual drydocking cost in US$ = 3,920,800