PI062 | Planned unavailability V3.0

Performance Indicator

This PI captures the ship’s agreed planned unavailability.


DefinitionThe number of hours planned for repairs and maintenance, including drydocking, in-water survey (IWS), modifications, hot / cold layup that are agreed between the ship manager and ship owner for the given period.
UnitHOURS
ScopeReported on a ship level
Calculation periodCaptured and reported on a rolling year basis
ReferencesThis Performance Indicator - PI062 - is used by the following Key Performance Indicators
KPI032Ship availability
PI003Actual unavailability
PI062Planned unavailability
Example

Q2-2018: 18 hours (ME maintenance)
Q3-2018: 140 hours (100 hours for planned Drydocking plus 40 hours steaming to shipyard)
Q4-2018: 4 hours (ME maintenance)
Q1-2019: 240 hours (Hot Lay-up)

Total planned unavailability on rolling year in Q1-2019: 402 hours